Payment Notices: Check The Sum, The Date And The Route
A payment notice needs more than the right total. Its basis, timing and service also matter. Build the process from the signed terms and the law for the job.
Independent quantity surveying and estimating consultants
Shrewsbury, supporting projects across the UK 01743 403120 info@qsconsultants.co.uk
Clear explanations of cost, contract, payment and delivery issues encountered across construction projects.
A payment notice needs more than the right total. Its basis, timing and service also matter. Build the process from the signed terms and the law for the job.
A job can make a profit and still use more cash than the firm has ready. Wages, deposits and materials may be paid long before the client pays for that work.
Records of changed work are strongest when made while the details can still be checked. A dated photo with a place and change code is more useful than an image no one can link.
You may claim one sum, have a lower sum valued and receive a third amount in the bank. Each figure needs its own label so the team can see why they differ.
Keep the final account live while the work is done. This gives the team time to agree clear items and fill record gaps before staff move on to the next job.
The site may call it Change 12 while the QS calls it VO 8. One shared reference links the scope, notices, price and next step so the team can trace the same event.
Last month's bills do not show all the work left to finish. A monthly commercial review should show where the job is heading and which cost or cash choices need action.
Before signing, check that the contract matches the work and risk you priced. A changed term can affect cost or cash even when the scope and headline sum look the same.
A delay notice should identify what happened and which work may be affected. A general complaint may leave the other side unclear and fail the process required by the contract.
A late drawing may delay a task without delaying the finish of the job. An extension of time case needs to show how the event moved the route to the contract end date.