What Should Your Monthly Job Review Tell You?

Last month's bills do not show all the work left to finish. A monthly commercial review should show where the job is heading and which cost or cash choices need action.

Last month's bills do not show all the work left to finish. A monthly commercial review should show where the job is heading and which cost or cash choices need action.

Can your cost meeting explain what moved and who will act next?

The monthly commercial review. Cost forecast: What will the job finish at?; Value and change: What is agreed or still open?; Cash: When will money move?; Actions: Who does what, by when?. Explain the moves since the last report.
Explain the moves since the last report.

Construction Commercial Review: Use One Reporting Basis

Set a cut-off date and check costs, orders, claims and the change register. Use a common format so jobs can be compared.

Show value and margin, cost to finish, work still to buy and payment status. Keep retention, final accounts and time risks in view.

Explain What Moved

State the cause, value and source of major moves since the last review. Keep firm sums apart from amounts still in doubt.

A saving needs evidence and an action that will deliver it. Show a possible saving on its own until its basis supports the forecast.

The report is complete. Which decision should change what happens on site?

Turn the monthly review into action
  1. Facts

    Confirm the cut-off and cost to finish.

  2. Movement

    Explain the cause and value of each change.

  3. Action

    Name the owner, decision and deadline.

QSEC · Use these checks with the facts and terms of your job.

End each material issue with an owner and due date, then check progress at the next review.

Finish With Clear Actions

Bring site, QS and finance views together. Keep full workings behind a short report on the points that need a choice.

Name who will act, by when and what the action should change. Check the result at the next review so the same issue does not return with no progress.

General guidance. Check your signed contract and the job facts. Get legal advice where needed.

General guidance This article is not project-specific contractual or legal advice. Review the signed contract and facts before acting.

Need a clearer commercial position on your project?

Discuss the requirement