Show the gap on each change. Instruction: Agreed authority or open point; Scope: Work each party has priced; Quantity / rate: The exact disputed basis; Next action: Evidence, owner and due date. A new total alone does not answer the reason for the gap.
QSEC insight

Your Change Price Is Still Not Agreed. What Is The Real Gap?

A change price may stay open because the two sides are discussing different points. Find whether the gap is the instruction, scope, quantity, rate or time effect before resending the total.

A change price may stay open because the two sides are discussing different points. Find whether the gap is the instruction, scope, quantity, rate or time effect before resending the total.

When a change is not agreed, which part of the claim is being challenged?

Show the gap on each change. Instruction: Agreed authority or open point; Scope: Work each party has priced; Quantity / rate: The exact disputed basis; Next action: Evidence, owner and due date. A new total alone does not answer the reason for the gap.
A new total alone does not answer the reason for the gap.

Variation Not Agreed? Show Both Positions

Put the claimed sum beside the sum assessed. Record scope and quantities agreed, then mark the rates or costs still in dispute.

Link each point to its terms, instruction and records. This view can help focus the talks better than another copy of the full claim.

Close Record Gaps

Find missing plans, quotes and site notes while they can still be checked. Show how the files support the amount claimed.

Keep notice and payment dates in view. Talking about value does not put the contract process on hold.

More emails will not close an unexplained gap. Is it scope, entitlement or the rate?

Find the actual point in dispute
  1. Claimed

    State your sum and supporting basis.

  2. Assessed

    Record the other party’s view and reason.

  3. Next action

    Answer the gap with proof and a due date.

QSEC · Use these checks with the facts and terms of your job.

Set out the precise difference and answer it with the relevant record while tracking notice and payment dates.

Record The Result

If part is agreed, say whether it is on account or final for that item. Update the register, account and forecast together.

Show a sound view of open values without treating them as firm cash. Get legal advice where rights, service or formal dispute steps need review.

Name who should reply to each open point and set a due date. Save their reply and use it to plan what the next meeting needs to resolve.

General guidance. Check your signed contract and the job facts. Get legal advice where needed.

General guidance This article is not project-specific contractual or legal advice. Review the signed contract and facts before acting.